HomeSponsors2009 CarPast CarsThe TeamAlumniVideosContact Us
 

2009

Construction Journal

 

 

 

 

 

 

 

 

March 20, 2009

Frame finished, powder coated and a visit to VTF

For the past two weeks the team has been going full out trying to get our frame and other parts finished so that we can send it all out to paint. There were many late nights, and our date to paint had to be pushed back by 3 days, but we finally got it all finished. There are now only a few loose ends before the car can be put on wheels, which will hopefully happen next week.

With the frame finally completed, we took it to CIC coatings, who have been sponsoring us for a few years now. We are all very impressed with how the paint turned out. We also made a trip to VTF inc this week to have our plastic parts formed.

 

February 23, 2009

Frame progress and new parts

It has been a long time since the last website update, but the car has made some steady progress during that time. The frame is now almost finished, and the car is expected to be on wheels within the next few weeks.

In the last two months we have also gotten a new transmission from CVTech, as well as machined a lot of the new parts for our car. Below is a new gearbox jackshaft ready to be sent our for gear cutting, and new rear hub adaptors.

December 9, 2008

RHOs Completed

Despite the exams, the team put in lots of time this week and completed the Roll Hoop Overhead tubes, that make up a large portion of the car's frame. With the RHOs completed, work has begun on the SIMs (Side Impact Member) tubes that run along the sides of the car.

Earlier this fall, a small package arrived from ISCAR tools. Inside it was their shipment of new machining tools, including changeable milling heads, high quality end mills and turning inserts. Queen's Baja would like to thank ISCAR, and look forward to using these tools.

 

November 28, 2008

Lowed Deck Completed

After countless hours of standing in front of a grinder, the lower deck of the car has been completed. Today the whole assembly is being welded together. Construction of the necessary jigs for the RHOs (roll hoop overhead) is beginning today, and the RHOs will be bent next week.

 

November 10, 2008

Construction Begins

With the frame design finalized, the team has begun fabrication of the 2009 car. As of the time of this post the firewall has been completed and we are awaiting a new shipment of welding rod before it can be welded in place.

 

September 11, 2008

Frosh Recruitment

Frosh week has now come and gone, and we have put together a sizable list of people who have expressed interest in joining the team. To anybody interested, there will be a meeting for new people on Monday, September 15 at 7:00 PM in McLaughlin Hall room 306. Everybody is welcome and no experience is necessary.

 

July 22, 2008

Website being updated

For the first time since last summer, the website is finally being updated. Watch for new things in the 2009 car section and follow the journal. Also watch for new promotional videos, they will be going up soon.